65 <br /> OCS Schools Impact Fee Report(DRAFT) <br /> SCHOOL CONSTRUCTION <br /> TischlerBise analyzed costs for school construction in the OCS system. Costs for completed and planned <br /> school projects in OCS were provided by the Orange County Finance Office and OCS.TischlerBise adjusted <br /> previous costs to current (2016 Q1) dollars, where appropriate, using the Turner Building Index, a well- <br /> known and widely available construction price index. Current school costs represent the average costs to <br /> construct elementary, middle, and high schools in the OCS System. As shown in Figure 9, construction <br /> costs average between$202 and $252 per square foot. Specifically,the costs are as follows—elementary: <br /> $202 per square foot; middle: $223 per square foot; and high: $219 per square foot. <br /> Figure 9. School Project Costs <br /> School Year Cost Index Factor I Adjusted Cost[11 Square Feet CostperSF Capacity <br /> Elementary School Prototype(per seat)[2] - $27,678 - $27,678 136.80 $202 1 ,$27,678 <br /> Gravelly Hill Middle 2006 $22,369,811 122% $27,362,821 122,793 $223 700 $39,090 <br /> Cedar Ridge High 2003 $27,987,060 156% $43,715,698 206,900 $211 1,000 $43,716 <br /> Planned Cedar Ridge High Addition[3] 2017 $12,583,000 N/A $12,583,000 50,000 $252 Soo $25,166 <br /> High Subtotal $56,298,698 256,900 $219 1,500 $37,532 <br /> $62,967,549 $83,689,196 379,830 $220 2,201 1 $38,023 <br /> 111 Adjusted using the Turner Building Cost Index,2016 First Quarter Forecast <br /> 121 Derived as a percentage of the CHCCS cost persq.ft.for elementary schools.TischlerBise defined a)the relationship between OCS and CHCCS of the average cost persq.ft.for all recent school projects and <br /> b)the relationship between CHCCS's elementary school and its middle and high schools.These two percentages are then multiplied by CHCCS's cost persq.ft.for middle schools to derive the OCS cost. <br /> 131 The cost estimate for this project is in 2015 dollars and was not index-adjusted.Adjusted cost subtotals and totals include this unadjusted cost. <br /> PORTABLE L <br /> Orange County currently uses portable classrooms for additional classroom capacity with a total of 6 <br /> classrooms in use currently.The cost for each portable classroom is$78,000, per Orange County staff. <br /> SUPPORT FACILITIES <br /> The impact fees also include costs to provide support facilities such as administrative office space, <br /> maintenance facilities,and bus garages. For OCS,support facilities include Board of Education office space <br /> and the Maintenance Shop.The joint-use Transportation Facility serves both school systems in the county <br /> and, therefore, costs are allocated to current enrollment in both districts (see Appendix A). Costs were <br /> confirmed with OCS staff.The following two figures reflect current LOS and cost factors for these facilities. <br /> Figure 10. Support Facilities–OCS <br /> Square cost Bldg <br /> Facility Feet Per Sq Ft cost <br /> Board of Education(OCS) 6,210 $200 $1,242,000 <br /> Maintenance Shop(OCS) 17,559 $200 $3,511,800 <br /> Current Total OCS Enrollment 7,526 <br /> Building LOS(sq.ft.per student) 3.16 <br /> Building Cost per Student $631.65 <br /> Source:Orange County Schools <br /> 14 <br />