Change Order <br /> No. 01-FINAL <br /> Date of Issuance: June 17,2014 Effective Date: June 17,2014 <br /> Project: McGowan Interceptor I Owner:Orange County,North Carolina Owner's contract No.: SRF#CS370884-02 <br /> Contract: McGowan Interceptor Date of Contract: February 28,2014 <br /> Contractor: Park Construction of NC,Inc. Engineer's Project No.: 13.01114 <br /> Post Office Box 500,Morrisville,North.Carolina 27560 <br /> The Contract Documents are modified as follows upon execution of this Change Order: <br /> Description: <br /> Credit for change in pipe bedding,Change to Manhole#11 to connect to existing sewer,Revisions to Michael <br /> Efland's easement,Temprorary relocation of existing force main,relocation of property owner fence,addition of <br /> sewer service for Madison Efland property,Final adjustment of actual installed quantities <br /> Attachments(list documents supporting change): <br /> _Table entitled:"Final Adjustment of Installed Quantities",emails from Park dated February 26 and April 30,2014, <br /> Frye Fence proposal dated April 24,2014,Letters from Park Construction dated April 17 and-28,2014 <br /> CHANGE IN CONTRACT PRICE: CHANGE IN CONTRACT TIMES: <br /> Original Contract Price: Original Contract Times: ❑ Working days N Calendar days <br /> Substantial completion(days or date): 180 <br /> $ 597,813.13 Ready for final payment(days or date): 210 <br /> gaefeme] [Deereese]from previously approved [R*Feme] [Deerease] from previously approved Change Orders <br /> Change Orders No.N/A to No.N/A: No.N/A to No.N/A: <br /> Substantial completion(days): N/A <br /> $ 0.00 Ready for final payment(days): N/A <br /> Contract Price prior to thi$Change Order: Contract Times prior to this Change Order: <br /> Substantial completion(days or date): 180 <br /> $ 597,813.13 Ready for final payment(days or date): 210 <br /> [Increase] [Deem Ease]of this Change Order: [kietease] [Decrease] of this Change Order: <br /> Substantial completion(days or date): 0 <br /> $ 470,589.95 Ready for final payment(days or date): 0 <br /> Contract Price incorporating this Change Contract Times with all approved Change Orders: <br /> Substantial completion(days or date): 180 <br /> $ 1.068.403.08 Ready for final payment(days or date): 210 <br /> REC ACCEP D ACCEP ' <br /> By: By: _ By. , <br /> ol <br /> VEngineRuth ized Signature) caner(Auril,rized Si nature) Contractor( uthori d Signature) <br /> Date: 1�-4".&.=lit Date: Date: V <br /> Approved by Funding Agency(if applicable): <br /> Date: <br /> EJCDC C-941 Change Order <br /> Prepared by the Engineers Joint Contract Documents Committee and endorsed by the Construction Specifications institute. <br /> Page I of 2 <br />