The Cedar Grove Community Center project development timeline is as follows: <br />TASK <br />PROPOSED <br />BEGINNING <br />DATE <br />END BY <br />DATE <br />BOCC Action: Final approval of bid documents prior to bid <br />11/18/14 <br />11/18/14 <br />Community Meeting on Programming and Operations <br />12/2014 <br />1/2015 <br />Project Bid process <br />11/9/14 <br />11/13/15 <br />BOCC Action: Bid Award (tentative upon BOCC calendar approval) <br />1 1/22/15 <br />1 1/22/15 <br />Construction, Commissioning, Opening (est. 8 months duration) <br />1 2/15/15 <br />1 10/30/15 <br />Progress photos will be provided for both projects during staff's presentation at the work <br />session. <br />FINANCIAL IMPACT: None at this time. Funding for operating the Cedar Grove Community <br />Center will need to be addressed in the FY 2015 -16 budget. <br />RECOMMENDATION(S): The Manager recommends the Board receive the update on the <br />progress of the Rogers Eubanks Neighborhood Association Community Center and the Cedar <br />Grove Community Center. <br />