accounted for properly. The final adjusting change order shows a net increase of $56,016. The <br />main reasons for this net increase are highlighted below. <br />• The estimated amount of rock along the 18" sewer line, for which Change Order #4 was <br />approved on December 2, 2013, was slightly larger than estimated ( +$23,880); <br />• The estimated amount of rock along the 12" sewer line was larger than estimated <br />( +$167,353); <br />• The amount of select fill (material brought in to replace rock removed or other unsuitable <br />soil) needed was higher than originally estimated, due to increased rock excavation <br />( +$64,500); <br />• Field conditions along the path of the 12" sewer line near a large pond required a more <br />expensive construction technique than originally estimated ( +$36,764); <br />• A portion of the 8" sewer line was cut from the originally bid scope of work, with <br />approximately 700 linear feet left in the contract. However, when the unit price sheet <br />establishing the contract amount was developed, the 8" gravity sewer line from the <br />original bid was mistakenly left out. Therefore, the budget for the project was developed <br />around an artificially low contract amount. The work was added back to the contract <br />amount as Change Order #5 ( +$42,359.35); <br />• Field conditions allowed for use of a much less expensive technology to cross three <br />streams with the 16" water line (- $265,134). <br />As mentioned above, these are the items that had the most influence on the amount of the <br />adjusting change order. The substantial savings realized by changing the type of bore used on <br />the water line should be noted. The net amount of these six items, along with the adjustments <br />needed to zero all the rest of the line items in the contract, makes up the final adjusting change <br />order amount. <br />The amount of the final adjusting change order is within the Manager's dollar amount to <br />approve, but approval of the additional money would exceed the project's budget. Therefore, <br />the change order must be approved by the BOCC and a budget amendment is required to <br />increase the budget to cover the additional cost. <br />FINANCIAL IMPACT: This project currently has an overall budget of $5,013,046. The overall <br />project budget will need to be increased by $56,016 to a total of $5,069,062 in order to cover <br />the cost of the final adjusting change order. The additional funds to cover the change order <br />would come from revenues received from the Article 46 Quarter -Cent Sales Tax. Budget <br />Amendment #1 -C provides for the additional funds of $56,016 from Article 46 Sales Tax <br />proceeds, and amends the Capital Project ordinance as follows: <br />Buckhorn Mebane Phase 2 ($56,016) - Project # 30040 <br />Revenues for this project: <br />FY 2014 -15 <br />Current <br />Budget <br />Oct. 7, 2014 <br />Amendment <br />FY 2014 -15 <br />Revised <br />Budget <br />Alternative Financing <br />$412561046 <br />$0 <br />$412561046 <br />Appropriated Fund Balance <br />$2001000 <br />$0 <br />$2001000 <br />From General Fund <br />$1351500 <br />$0 <br />$1351500 <br />Article 46 Sales Tax Proceeds <br />$4211500 <br />$561016 <br />$4771516 <br />Total Project Funding <br />$510131046 <br />$561016 <br />$510691062 <br />