Orange County NC Website
f. McGowan Sewer Interceptor Additional Rock Allowance and Approval of Budqet <br /> Amendment#9-E <br /> The Board considered approving Budget Amendment#9-E adding additional rock <br /> contingency to the McGowan Sewer Interceptor capital project budget and authorizing the <br /> Manager to sign. <br /> Chair Jacobs said this is on the regular agenda mainly as an informational item due to <br /> the costs. <br /> Kevin Lindley reviewed the following project overview as included in the abstract: <br /> This project has been underway since March 17, 2014. The overall project is approximately <br /> 85% complete and consists of 2,400 linear feet of 12" gravity sewer line and de-commissioning <br /> of the McGowan Creek Sewer Pump Station. The installation of this gravity sewer line will allow <br /> the County to take the 26 year-old McGowan Creek Pump Station off line, which reduced the <br /> annual maintenance costs for the system and avoids costly reconstruction of the aging pump <br /> station (see Attachment 1). <br /> The original estimated rock quantity for the 12" sewer line was 2,000 cubic yards. However, <br /> after constructing approximately 2,000 linear feet (83%) of this line, the Contractor has <br /> excavated 4,665 cubic yards of rock. Because of the large quantity of rocky material, the <br /> Contractor has been using a special back hoe designed to break up the blasted rock, which <br /> allowed it to be placed back in the trench. This avoids having to haul the rock out by the <br /> truckload for disposal and having to purchase and haul in select fill dirt to replace the rock that <br /> was removed. <br /> The County's engineering consultant, McGill Associates, is estimating that there could be an <br /> additional 1,209 cubic yards of rock left to be excavated to finish this project. If the consultant's <br /> estimate proves correct, the total rock excavated for this 12" sewer line would be 5,873 cubic <br /> yards. When compared to the original estimate of 2,000 cubic yards, the difference is 3,873 <br /> cubic yards. <br /> The rock excavation line item is paid at $120 per cubic yard of rock excavated, so adding an <br /> additional rock excavation amount of 3,873 cubic yards will increase the construction costs by <br /> $464,760. This estimate is based the best available data and is conservatively estimated to be <br /> sufficient to cover all rock for the rest of this project. This project has a unit price contract so <br /> that a contractor is paid per unit, in this case cubic yards, as the rock is excavated. The <br /> contractor will only be paid for the amount of rock excavated, regardless of the amount <br /> available in the budget for that particular line item. <br /> The project is being funded by a State Revolving Fund (SRF) Loan. The current available loan <br /> amount is $774,904. The original construction contract was for $597,813, and the engineering <br /> design and construction oversight was $94,200, leaving $82,891 to cover ancillary costs and <br /> contingency. To date, there have been change order requests from the contractor and other <br /> ancillary costs against this contingency in the net amount of approximately $40,000, leaving <br /> approximately $42,891 to go towards the extra rock excavation cost. <br /> Additionally, $57,814 was appropriated to cover costs of the project which cannot be <br /> reimbursed through loan proceeds, such as the loan origination fee and easement costs. This <br /> amount will still be sufficient to cover the costs for which it was budgeted. <br /> Commissioner porosin asked how likely it is for staff to anticipate these kinds of <br /> obstacles. He asked if this is unavoidable in these kinds of projects, or if something should <br /> have been done. <br />