Orange County NC Website
11.02 Allowances <br /> A. It is understood that Contractor has included in the Contract Price all allowances so named in the <br /> Contract Documents and shall cause the Work so covered to be performed for such sums and by <br /> such persons or entities as may be acceptable to Owner and Engineer. <br /> B. Cash Allowances: <br /> 1. Contractor agrees that: <br /> a. the cash allowances include the cost to Contractor(less any applicable trade discounts) of <br /> materials and equipment required by the allowances to be delivered at the Site, and all <br /> applicable taxes; and <br /> b. Contractor's costs for unloading and handling on the Site, labor, installation, overhead, <br /> profit, and other expenses contemplated for the cash allowances have been included in <br /> the Contract Price and not in the allowances, and no demand for additional payment on <br /> account of any of the foregoing will be valid. <br /> C. Contingency Allowance: <br /> 1. Contractor agrees that a contingency allowance, if any, is for the sole use of Owner to <br /> cover unanticipated costs. <br /> D. Prior to final payment, an appropriate Change Order will be issued as recommended by Engineer <br /> to reflect actual amounts due Contractor on account of Work covered by allowances, and the <br /> Contract Price shall be correspondingly adjusted. <br /> 11.03 Unit 'rice Work <br /> A. Where the Contract Documents provide that all or part of the Work is to be Unit Price Work, <br /> initially the Contract Price will be deemed to include for all Unit Price Work an amount equal to <br /> the sum of the unit price for each separately identified item of Unit Price Work times the <br /> estimated quantity of each item as indicated in the Agreement. <br /> B. The estimated quantities of items of Unit Price Work are not guaranteed and are solely for the <br /> purpose of comparison of Bids and determining an initial Contract Price. Determinations of the <br /> actual quantities and classifications of Unit Price Work performed by Contractor will be made by <br /> Engineer subject to the provisions of Paragraph 9.07. <br /> C. Each unit price will be deemed to include an amount considered by Contractor to be adequate to <br /> cover Contractor's overhead and profit for each separately identified item. <br /> D. Unless otherwise stipulated in the Contract Documents, for Unit Price Work, Contractor shall be <br /> paid an amount equal to the sum of the unit price for each separately identified item of Unit Price <br /> Work times the actual quantity of each item as determined by the Engineer pursuant to paragraph <br /> 9.07. Variations between the actual quantity and the estimated quantity for items of Unit Price <br /> Work,including increases and decreases in quantities, as a result of any Change Orders,shall not <br /> serve as a basis for an adjustment in the unit price of the item. <br /> EJCDC C-700 Modified Standard General Conditions of the Construction Contract <br /> Copyright(D 2007 National Society of Professional Engineers for EJCDC. All rights reserved. <br /> Page 58 of 81 <br />