' 3. To the fullest extent permitted by Laws and Regulations, Contractor shall indemnify and
<br /> hold harmless Owner and Engineer, and the officers, directors, members, partners,
<br /> employees, agents, consultants and subcontractors of each and any of them from and
<br /> against all claims, costs, losses, and damages (including but not limited to all fees and
<br /> charges of engineers, architects, attorneys, and other professionals and all court or
<br /> arbitration or other dispute resolution costs) arising out of or relating to any claim or
<br /> ' action, legal or equitable, brought by any such owner or occupant against Owner,
<br /> Engineer, or any other party indemnified hereunder to the extent caused by or based upon
<br /> Contractor's performance of the Work.
<br /> 4. Only materials and equipment that are to be used directly in the Work shall be brought to
<br /> and stored on the Project site by Contractor. After equipment is no longer required for the
<br /> ' Work, it shall be promptly removed from the Project site. If Contractor uses any portion
<br /> of the new Work prior to the date of Substantial Completion of the entire Work, such
<br /> items shall be restored to their new condition.
<br /> B. Removal of Debris during Performance of the Work: During the progress of the Work
<br /> Contractor shall keep the Site and other areas free from accumulations of waste materials,
<br /> ' rubbish, and other debris. Removal and disposal of such waste materials, rubbish, and other
<br /> debris shall conform to applicable Laws and Regulations.
<br /> C. Cleaning: Prior to Substantial Completion of the Work Contractor shall clean the Site and the
<br /> Work and make it ready for utilization by Owner. At the completion of the Work Contractor
<br /> shall remove from the Site all tools, appliances, construction equipment and machinery, and
<br /> ' surplus materials and shall restore to original condition all property not designated for alteration
<br /> by the Contract Documents.
<br /> D. Loading Structures: Contractor shall not load nor permit any part of any structure to be loaded
<br /> ' in any manner that will endanger the structure, nor shall Contractor subject any part of the Work
<br /> or adjacent property to stresses or pressures that will endanger it.
<br /> ' 6.12 Record Documents
<br /> A. Contractor shall maintain in a safe place at the Site one record copy of all Drawings,
<br /> Specifications, Addenda, Change Orders, Work Change Directives, Field Orders, and written
<br /> interpretations and clarifications in good order and annotated to show changes made during
<br /> construction including, but not necessarily limited to, (i) deviations from the Drawings and
<br /> Specifications made during construction; (ii) details in the Work not previously shown; (iii)
<br /> changes to existing conditions or existing conditions found to differ from those shown on the
<br /> ' Drawings; (iv) the actual installed position of all mechanical, electrical equipment, piping,
<br /> ductwork, access panels, valves, drains, stub outs, etc.; and (v) such other information as Owner
<br /> or Engineer may reasonably request. These record documents together with all approved
<br /> ' samples and a counterpart of all approved Shop Drawings will be available to Engineer and
<br /> Owner for reference. Contractor's Record Documents shall be available for review by Engineer
<br /> as part of the pay application process. A pay application will not be considered until the Record
<br /> Documents are shown complete through that application period. Upon completion of the Work,
<br /> these Record Documents, Samples, and Shop Drawings will be delivered to Engineer for Owner.
<br /> Final payment and any retainage shall not be due and owing to Contractor until the Record
<br /> ' Documents,marked by Contractor, as required above are delivered as required above.
<br /> EJCDC C-700 Modified Standard General Conditions of the Construction Contract