2 <br /> The rock excavation line item is paid at $120 per cubic yard of rock excavated, so adding an <br /> additional rock excavation amount of 3,873 cubic yards will increase the construction costs by <br /> $464,760. This estimate is based the best available data and is conservatively estimated to be <br /> sufficient to cover all rock for the rest of this project. This project has a unit price contract so <br /> that a contractor is paid per unit, in this case cubic yards, as the rock is excavated. The <br /> contractor will only be paid for the amount of rock excavated, regardless of the amount <br /> available in the budget for that particular line item. <br /> The project is being funded by a State Revolving Fund (SRF) Loan. The current available loan <br /> amount is $774,904. The original construction contract was for $597,813, and the engineering <br /> design and construction oversight was $94,200, leaving $82,891 to cover ancillary costs and <br /> contingency. To date, there have been change order requests from the contractor and other <br /> ancillary costs against this contingency in the net amount of approximately $40,000, leaving <br /> approximately $42,891 to go towards the extra rock excavation cost. <br /> Additionally, $57,814 was appropriated to cover costs of the project which cannot be <br /> reimbursed through loan proceeds, such as the loan origination fee and easement costs. This <br /> amount will still be sufficient to cover the costs for which it was budgeted. <br /> FINANCIAL IMPACT: This project currently has a construction contract in the amount of <br /> $597,813. Adding the rock allowance contingency as outlined above would increase the <br /> construction contract by $464,760. These extra funds would come from remaining contingency <br /> of $42,891 and a requested increase of $421,869 in the SRF loan financing this project. <br /> Budget Amendment #9-E provides for the additional funds of $421,869 from SRF proceeds, <br /> and amends the Capital Project ordinance as follows: <br /> McGowan Creek Outtall — Project# 30043 <br /> Revenues for this project: <br /> FY 2013-14 June 17, 2014 FY 2013-14 <br /> Current Amendment Revised <br /> Budget Budget <br /> SRF Loan Proceeds $774,904 $421,869 $1,196,773 <br /> Article 46 Sales Tax Proceeds $57,814 $0 $57,814 <br /> Total Project Funding $832,718 $421,869 $1,254,587 <br /> Appropriations for this project: <br /> FY 2013-14 June 17, 2014 FY 2013-14 <br /> Current Amendment Revised <br /> Budget Budget <br /> Professional Services $94,200 $0 $94,200 <br /> Construction $680,704 $421,869 $ 1,102,573 <br /> Easements, Loan Orig., misc. $57,814 $0 $57,814 <br /> Total Costs $832,718 $421,869 $ 1,254,587 <br /> RECOMMENDATION(S): The Manager recommends the Board- <br /> 1. Approve Budget Amendment #9-E adding $464,760 in rock contingency to the <br /> McGowan Creek Outfall project construction contract and authorizing the request for an <br /> additional $421,869 in SRF loan funding; and <br /> 2. Authorize the Manager to sign on behalf of the Board the change order for the additional <br /> rock allowance and any documents related to the pursuit of additional SRF loan funding <br /> as outlined in Item 1. <br />