Orange County NC Website
1. Review with Engineers /Designers revealed that previously proposed Phase 2 Mezzanine (ice) is not feasible Project has been re- scoped to create national class <br />recreation facility adding indoor turf and court. Project defined to straddle two years <br />a Phase 1 is the originally contemplated pool mezzanine of 5,400 sq ft. featuring new member lockers, dedicated spin /row /yoga fitness room and 1,800 sq <br />ft. senior/ adult cardio/ strength center <br />b Phase 2 is a new building addition for and indoor turf field to be used for soccer, lacrosse, senior walking, running, kidsplex, kickball and proprietary RFP <br />programs such as Lil Kickers NOTE Projected annual revenues related to this project are anticipated to cover the annual debt service required for this <br />project <br />c Phase 3 is anew regulation size basketball court including bleachers. NOTE Projected annual revenues related to this project are anticipated to cover <br />the annual debt service required for this project. <br />d Town of Hillsborough signed off on parking plan even prior to recent land acquistion, which now facilitates optimal parking planning <br />Update Given recent land acquisition, project under review to determine savings of less start up /shut down with phases 2 & 3 consolidated jn 2015 16 <br />Added benefits of less construction related disruption to members and customers <br />2 Movable bleachers to add seating for specatator rink and pool based events ( portable to pool) Completed with funds from Ops Budget <br />3 Rinkfloor repair split into two projects of $75K each ( Deferred in FY 13 -14 and combined into one project in FY 17 -18 with savings of $75,000) <br />4 Pool Electronic Timer and scoreboard. Scoreboard is 19 years old and failing Repairs are costly and increasingly less feasible Required for revenue generating <br />swim meets and lane training (Completed) <br />5 Increasingly, youth and adult teams are co -ed Proposal to convert referee room into girls /women's change room and build replacement ref room and storage in <br />part of Zamboni room To be completed June 2014 <br />6. Outside pavilion to be built in flat grassy area to the west of pond To be used for Kidsplex outdoor activities; rented for parties Orange County Charter School has <br />expressed interest in partnering There may also be grants available. ( More efficient to locate as part of Major Expansion Project in 2015 -16) <br />7 Men's and Women's main lobby bathrooms are worn Replace flooring, stall dividers; paint, ceiling tiles. Efficient lighting (motion sensor) and low flow plumbing <br />fixtures Lower counters and child appropriate toilets. Add safe, locked storage for cleaning supplies To be completed June 2014 <br />8 Servers upgraded out of equipment repair /replace budget in 2012/13. Building wide telephone /intercom still required To be done using operating funds <br />8(a) Facilitates 1,834 additional GroupX space for programs Results in $312,000 incremental annual revenue To be completed June 2014 <br />9 Major cardio equipment typically has a useful life of 3 years with the heavy usage from increasing Sportsplex membership While regular maintenance programs <br />can extend life, it is appropriate to maintain a budgeted contingency based on industry replacement standards. <br />10 Similar to above With growth in Kidsplex program we expect more capital needs for this program <br />11 Pumps and boilers have the least useful life of all mechanical classes of equipment Contingency for replacement. <br />12 Contingency for HVAC equipment and major IT equipment such as server <br />13 Inflatables. This is one of the lowest cost ways to generate revenue Can be used for Kidsplex, Parties and for fee admission using renovated lobby space. Quality <br />inflatables can be purchased for $2,500 to $3,000 each Payback is less than one year (Better space planning options if deferred to after Major Expansion Project in <br />2015 -16 <br />