ONE COMPANY Maks;Salutions,. Attachment 1
<br /> April 3,2014
<br /> Gayle Wilson
<br /> Solid Waste Management Director
<br /> Orange County Solid Waste Management Department
<br /> 1207 Eubanks Road
<br /> Chapel Hill,NC 27516
<br /> Re: Orange County MSW Landfill
<br /> Closure Construction
<br /> HDR Project No.350207-142839-018
<br /> Dear Mr.Wilson:
<br /> HDR Engineering, Inc. of the Carolinas(HDR)has reviewed the bids for the Orange County MSW Landfill
<br /> Closure Construction project. The project consists of constructing a cap over the entire lined landfill facility
<br /> of approximately 25 acres. Construction activities include surface preparation,placement of a 40 mil LLDPE
<br /> geomembrane and geocomposite drainage layer,placement of an 18-inch thick soil cushion and 6-inch thick
<br /> topsoil layer over the geosynthetic components of the final cover system, stormwater controls, erosion and
<br /> sediment control measures,and other incidental work.
<br /> The following information is provided regarding our evaluation of bids received.
<br /> Background
<br /> Six bids were received for the Orange County MSW Landfill Closure Construction project by 3:00 p.m. on
<br /> March 25,2014 from the following contractors and are listed from lowest to highest base bids:
<br /> Base Bid Bid Alternate No.1 Bid Alternate No.2 Irregularities
<br /> Contractor
<br /> (On-Site Soils) (Off-Site Soils) (Off-Site Topsoil) (See Notes)
<br /> T&K Construction,LLC $3,340,600 $3,766.600 $3,543,100 No
<br /> Southeast Environmental
<br /> $3,544,000 $4,740,000 $3,822,000 Yes'
<br /> Contracting,Inc.
<br /> Triangle Grading&Paving,Inc. $3,687,539 $4,679,033 $4,057,369 Yes2
<br /> Thalle Construction Co.Inc. $3,847,698 $4,360,687 $3,996,777 No
<br /> Sargent Corporation $4,209,400 $4,980,300 $4,369,125 No
<br /> Rifenburg Construction Inc. $6,155,378 $6,130,378 $6,655,378 Yes2
<br /> Notes: 1.Did not submit Subcontractor and Supplier Tabulation.
<br /> 2.Did not submit Qualification Statement.
<br /> Tabulation
<br /> The above-referenced bids were examined for accuracy and compliance with the bid requirements. A certified
<br /> tabulation is enclosed and includes all numerical information provided with the bid and any irregularity that
<br /> was discovered. As shown in the above table, three of the bids (Southeast Environmental Contracting, Inc.;