Orange County NC Website
. . z <br /> - Extra work to avoid an unmarked 16" force main <br /> - Reroute a 4" water main <br /> - Delays due to easement dispute <br /> - Revised rock contingency for water line: $ 52,172.00 <br /> Net Contract Price Change for CO#1: $ 0.00 <br /> CO#2 $ 2,242.50 <br /> - Cost due to resurveying/relayout of sewer S-1 <br /> - Done to avoid a potentially significant <br /> cultural/archaeological site on the Rohl <br /> property <br /> Revised Contract Price after Change Orders: $49,0189788.24 <br /> SCHEDULE <br /> The project start date was 4/16/2013. Based on the original schedule the allowed <br /> substantial completion date would have been 4/16/2014, or 365 days. C0#1 added <br /> an additional 57 days due to delays in obtaining easements and the time to <br /> complete the extra work. This extended the contractually allowed substantial <br /> completion date to 6/12/2014. <br /> CO#2 requests an additional .8 days due to inclement weather, which would push <br /> the allowed substantial completion date out to 6/20/2014. <br /> Please call or email with any questions. <br />