Orange County NC Website
J.F. Wilkerson Contracting Co., Inc. <br /> PO Box 183 <br /> Morrisville, NC 27560 <br /> CHANGE ORDER REQUEST <br /> Engineer: Hobbs Upchurch Associates <br /> Owner: Orange County <br /> Contractor: J.F. Wilkerson <br /> Job: Buckhorn—Mebane EDD Phase 2 <br /> Project Manager: Michael Coates <br /> Description of extra work/materials: <br /> On Tuesday June 25, 2013 Wilkerson crew encountered a 16"DIP force main on two <br /> sides of Man Hole 26 (existing) located near the Mebane lift station in Alamance County. <br /> The Force main is not shown on the bid plans, nor the construction plans. <br /> Change order request is for extra work,materials, and time lost due to excavating under <br /> and around the force main located in very close proximity to existing Man Hole#26. <br /> Tuesday June 25: Found the 16"Force Main 5 feet south& 5 feet east of MH 26 <br /> Wednesday June 26: Transport additional trench box,pumps, generator, stone to site. <br /> Penhall Core 24"hole in MH 26, extra time and up charge for working in cramped area <br /> between 167M and MH 26. <br /> Thursday June 27: Additional day spent excavating under force main,pumps, etc. <br /> Friday June 28: Lay one joint 18"DIP sewer under the 16"force main through the two <br /> trench boxes/ shields <br /> Equipment& Materials: <br /> Excavator: Cat 330 or equal @$700 per day(2 days) 1400 <br /> Loader: Cat 928 or equal @$300 per day(2 days) 600 <br /> Rammax: $85 per day(2 days) 170 <br /> Truck and trailer: $150 per day(1 day) 150 <br /> Pickup for crew: $75 per day(2 days) 150 <br /> Tool trailer: $150 per day(2 days) 300 <br /> Electric pump &25 KW generator(4 days inc. weekend) $150 per day 600 <br /> Stone: 40 tons approx. #57 washed stone a,$30 per ton 1200 <br /> Total Equipment& materials: $4570 <br /> Labor: <br /> Project Manager on site: 2 additional days 1000 <br /> Project Manager weekend: 1/2 additional day @ $500 250 <br /> Penhall extra charge for time and cramped area between MH 26 & 16"FM TBD <br /> Truck driver: 8 additional hours @$25 200 <br /> Foreman with 4 man crew: 16 additional regular time hours A $165 2,640 <br /> Total labor: $4,090 <br /> Total equipment,materials, and labor: 8,660 <br /> 15%Fee 1,299 <br /> Total additional compensation request: $9,959 <br />