Orange County NC Website
The project start date was 4/16/2013. Based on the original schedule the allowed <br /> substantial completion date would have been 4/16/2014, or 365 days. This change <br /> order requests an additional 57 days due to delays in obtaining easements and the <br /> time to complete the extra work. The addition of 57 days will extend the <br /> contractually allowed substantial completion date to 6/12/2014. <br /> Please call or email with any questions. <br />