Change Order <br /> No, 3 <br /> Date of Issuance: August 16,2012 Effective Date: August 16,2012 <br /> Project:Buckhorn Area North of I-85 and Owner:Orange County, Owner's Contract No.: SRF:CS370884-01 <br /> Efland Sewer System Improvements North Carolina STAG: XP95456411 <br /> Contract:Buckhorn Area North of 1-85 and Efland Sewer System Date of Contract: August 31,2011 <br /> Improvements <br /> Contractor:J.F. Wilkerson Contracting Company,Inc. Engineer's Project No.: 1.1.01111 <br /> The Contract Documents are modified as follows upon execution of this Change Order: <br /> Description: <br /> 1) Replace vented manhole ring and covers with solid ring and covers per the City of Mebane's request <br /> 2) Addition of sewer service installation through rock of$200.00/LF with an estimated total quantity of 70OLF <br /> 3) Delay due to and demolition of the discovered,unknown,Ruritan Club Septic Tank <br /> 4) Final adjustment of actual installed quantities in the Buckhom Section <br /> Attachments(list documents supporting change): <br /> J.F. Wilkerson letters dated February 8,2012,April 19,2012,May 15,2012,and June 22,2012 and McGill <br /> Associates letters dated March 23,2012 and June 20,2012. <br /> CHANGE IN CONTRACT PRICE: CHANGE IN CONTRACT TIMES: <br /> Original Contract Price: Original Contract Times: [❑ Working days ®Calendar days <br /> Substantial completion(days or(late): 450 Days <br /> $ 2,942,954.46 Ready for final payment(days or date): 450 Days <br /> [Increase] [Decrease] from previously approved [Increase] [Decrease] from previously approved Change Orders <br /> Change Orders No. to No.2: No. to No.2: <br /> Substantial completion(days): 90 Days <br /> $ 243,765.72 Ready for final payment(days): 90 Days <br /> Contract Price prior to this Change Order: Contract Times prior to this Change Order: <br /> Substantial completion(days or(late): 450 Days <br /> $ 3,186,720.18 Ready for final payment(days or date): 450 Days <br /> [Increase] [Dees ease]of this Change Order: [Increase] [tee]of this Change Order: <br /> Substantial completion(days or gate): 0 Days <br /> $ 92 670.50 Ready for final payment(days or date): 0 Days <br /> Contract Price incorporating this Change Contract Times with all approved Change Orders: <br /> ^ Substantial completion(days or date): 540 Days <br /> $ 3,279,390.68 Ready for fi atjlaiyment(days or date): 540 Days <br /> RECD -w-CCE ACCEPTED: <br /> By: By: Tui-4L By' <br /> Enginee A4tutho ed Signature) Owner�uthor zed Signature) o or(Authorized Signature) <br /> Date: ��-�t*xts-1�t'2.._ Date. ' % 1 '�-�-� Da:e: — <br /> Approved by Funding Agency(if applicable): <br /> Date: <br /> EJCDC C-941 Change Order <br /> Prepared by the Engineers Joint Contract Documents Committee and endorsed by the Construction Specifications Institute. <br /> Page 1 of 1 <br />