Orange County NC Website
r <br /> Y <br /> CHANGE ORDER Distributed To: <br /> G701 ® Owner ® Contractor 0 Fly Architect ❑ Subcontractor <br /> ❑ Field ❑ Other <br /> PROJECT: Piedmont Food&Agricultural Processing Ctr. CHANGE ORDER NO: 2 <br /> Valley Forge Rd. <br /> Hillsborough, NC 27278 DATE: December 14,2011 <br /> PROJECT NO: 0910 <br /> TO: Morlando Construction Company, LLC CONTRACT DATE: November 15,2010 <br /> 8604 Cliff Cameron Dr.Suite 155 <br /> Charlotte, NC 28269 CONTRACT FOR: General Construction <br /> The contract is changed as follows: <br /> fl C 1,r *.Wgi� � � 1"mbN <br /> 1 6,566.00 COC#14-Eelctrical Connection for Cooler/Freezer package-Panel to disconnect <br /> 2 19,934.00 COC#15-Freezer Floor Slab with Epoxy . <br /> 3 9,280.00 COC#16-Electrical Connection for Cooler/Freezer package-Disconnect to units �r <br /> 4 4,344.00 1 COC#17R-Electrical connections for used Fryer-Revised to upsize conductors,breakers&conduit <br /> 40,124.00 TOTAL <br /> The original Contract Sum was $ 802,470.00 <br /> Net change by previously authorized Change Orders CO#1 $ -13,536.00 <br /> The Contract Sum prior to this Change Order was $ 788,934.00 <br /> The Contract Sum will be increase by this Change Order in the amount of $ 40,124.00 <br /> The new Contract Sum including this Change Order will be $ 829,058.00 <br /> The Contract Time will be unchanged by. . . . . . . . . . . . . . . . . . . . . . . . . . . . ( 0 )days. <br /> The date of Substantial Completion as of the date of this Change Order therefore is May 5,2011 <br /> Accepted By: <br /> Morlando Construction, LLC Corley Redfoot Zack, Inc. Orange County, North C r lina <br /> CONTRACTO ARCHITECT OWNE <br /> By is Morlando y: rA:2jt(IV 45, FA Y: -t< <br /> �Jli�V1 <br /> Date Date Date <br /> Page 1 Of 1 <br /> TORGO SOFTWARE http:/Mww.torgo.net/01996-2007 ALL RIGHTS RESERVED <br />