<br />TABLE 3. .Estimated Installation Costs of New Water Lines and.
<br />Service Connections for 93 Properties in the fox
<br />Meadow Vicinity (September 2011).
<br />Size and Material Units Quantity Cost Total
<br />8" DIP Waterline LF 7953 $34 $267,300
<br />8"x 8" Tee EA 3 $1,062 $3,185
<br />8" x 8" Cross EA 1 $1,713 $1,713
<br />8" Fittings EA 45 $717 $32;262
<br />- 8" Gate Valves EA 22 $1,540 $33,880
<br />6" DIP Waterline LF 1093 $23 $24,855
<br />8" x 6" Tee EA 15 $1,Ob2 $15,930
<br />6" Gate Valve EA 15 $1,128 $16,920
<br />8"x6" Reducer EA 3 $527 $1,581
<br />4" DIP Waterline LF 816. $17 $13,627
<br />4" Gate Vales EA 3 $698 $2,094
<br />8"x4" Tee EA 3 $504 $1,512
<br />Fire Hydrant EA 15 $1;812 $27,177
<br />2" Gate Valve EA 6 $526 $3,157
<br />2" Blowoff Assembly EA 8 $1,000 $8,00.0
<br />8" Tap and Saddle EA 93 $202 $18,754
<br />3/4" Copper Service Line LF 2325 $14 $31,457
<br />Meter Box and Setter EA 93 $124 $11,519
<br />Excavation LF 9862 $41 $404,342
<br />Site Restoration LF 98.62 $21 $209,568
<br />Pavement Replacement SQ YD 1095 $120 $131,400
<br />Design LS 1 $75,000 $75,000
<br />Traffic Control LS 1 $20,000- $20,000
<br />Mobilization 10% 1 $135,523 $135,523
<br />Site Prep 5% 1 $67,762 $67,762
<br />Permitting 3% 1 $40,657. $40,657
<br />
<br />Construction Total $1,599,174
<br />Engineering Cost (10%J $159,917
<br />Construction Observation (5%~ $79 959
<br />Total $1,839,050
<br />Contingency (20%J $367,810
<br />Connection Costs (OWASA Availability Fees + Meter and Installation Costs)1 $319,920
<br />Grand Total Z $2,526,781
<br />1. Includes residential water availability fees as of October 1, 2011, based on 2,500 square foot
<br />home (fees range from $1,226 to $7,394 depending on home size), plus O WASH meter.
<br />installation. Does not include cost of service line from meter to the house.