Orange County NC Website
s , <br /> *=-rA1A <br /> Document G701 TM- 2001 Instructions <br /> Change Order <br /> GENERAL INFORMATION <br /> Purpose <br /> AIA Document G701 is for implementing changes in the Work agreed to by the Owner,Contractor and Architect. <br /> Execution of a completed G701 indicates agreement upon all the terms of the change,including any changes in <br /> the Contract Sum(or Guaranteed Maximum Price)and Contract Time. <br /> Use of Current Documents <br /> Prior to using any AIA Contract Document,users should consult www.aia.org or a local AIA component to verify <br /> the most recent edition. <br /> Reproductions <br /> This document is a copyrighted work and may not be reproduced or excerpted from without the express written <br /> permission of the AIA.There is no implied permission to reproduce this document,nor does membership in The <br /> American Institute of Architects confer any further rights to reproduce this document. <br /> The AIA hereby grants the purchaser a limited license to reproduce a maximum of ten copies of a completed <br /> G701,but only for use in connection with a particular project.The AIA will not permit reproduction outside of the <br /> limited license for reproduction granted above,except upon written request and receipt of written permission from <br /> the AIA. <br /> Rights to reproduce the document may vary for users of AIA software. Licensed AIA software users should <br /> consult the End User License Agreement(EULA). <br /> To report copyright violations of AIA Contract Documents,e-mail The American Institute of Architects'legal <br /> counsel,copyright @aia.org. <br /> COMPLETING THE G701 FORM <br /> Description of Change in the Contract <br /> Insert a detailed description of the change or reference specific exhibits describing,in detail,the change to be <br /> made in the Contract by this Change Order.Include any drawings,specifications,documents or other supporting <br /> data to clarify the scope of the change. <br /> Determination of Costs <br /> Insert in the blanks provided,or strike out the terms in parentheses that do not apply,the original Contract Sum or <br /> Guaranteed Maximum Price;the net change by previously authorized Change Order(note that this does not <br /> include changes authorized by Construction Change Directive unless such changes were subsequently agreed to <br /> by the Contractor and recorded as a Change Order);the Contract Sum or Guaranteed Maximum Price prior to this <br /> Change Order;the amount of increase or decrease,if any,in the Contract Sum or Guaranteed Maximum Price; <br /> and the new Contract Sum or Guaranteed Maximum Price as adjusted by this Change Order. <br /> Change in Contract Time <br /> Insert in the blanks provided,and strike out the unused terms in parentheses,the amount(in days)of the increase <br /> or decrease,if any in the Contract Time.Also insert the date of Substantial Completion,including any adjustment <br /> effected by this Change Order. <br /> EXECUTION OF THE DOCUMENT <br /> When the Owner and Contractor,in occurrence with the Architect,have reached agreement on the change to be <br /> made in the Contract,including any adjustments in the Contract Sum(or Guaranteed Maximum Price)and <br /> Contract Time,the G701 document should be executed in triplicate by the two parties and the Architect,each <br /> retaining an original. <br /> AIA Document G701 TM—2001.Copyright @ 1979,1987,2000,and 2001 by The American Institute of Architects.All rights reserved.WARNING:This <br /> AIA®Document is protected by U.S.Copyright Law and International Treaties.Unauthorized reproduction or distribution of this AIO Document, <br /> or any portion of it,may result in severe civil and criminal penalties,and will be prosecuted to the maximum extent possible under the law. <br /> Purchasers are permitted to reproduce ten(10)copies of this document when completed.To report copyright violations of AIA contract Documents,e-mail <br /> The American Institute of Architects'legal counsel,copyright @aia.org. <br />