<br />Lands Legacy
<br />Capital Project Ordinance
<br />Be it ordained by the Orange County Board of County Commissioners that pursuant to
<br />Section 13.2 of Chapter 159 of the General Statutes of North Carolina, the following
<br />capital project is hereby adopted.
<br />Section 1. The project authorized provides funds to protect identified natural areas
<br />and prime forestlands, and preserve critical cultural and archaeological
<br />sites. In addition funds may be used to acquire lands for future park sites,
<br />farmland conservation easements, and nature preserves. The BOCC
<br />approves transferring $450,000 of this project to the Unallocated Project
<br />Account to be closed as of June 30, 2010. The BOCC approves the
<br />appropriation of $111,636 ($102,299 sales tax revenues and $9,337
<br />County Capital Projects Fund Balance) to replace 2001 Bond Funds.
<br />Section 2. The officers of the County are hereby directed to proceed with the project
<br />within the budget contained herein.
<br />Section 3. The following revenue is anticipated to complete this project:
<br />Section 4.
<br />	Through FY
<br />2009-10	Amended June
<br />15, 2010	Through FY
<br />2009-10
<br />Sales Tax	$3,966,016	($440,663)	$3,525,353
<br />1997 Bonds	$2,700,000	$0	$2,700,000
<br />2001 Bonds	$5,250,000	-$111,636	$5,138,364
<br />2004 Two-Thirds Net Debt	$300,000	$0	$300,000
<br />Grant Funds	$421,950	$0	$421,950
<br />Debt Financin	$2,800,000	$0	$2,800,000
<br />Other(Transfer from Other
<br />Funds & Fund Balance)	
<br />$2,241,611	
<br />$102,299	
<br />$2,343,910
<br />Total Funding	$17,679,577	($450,000)	$17,229,577
<br />The following amount is appropriated for this project:
<br />	Through FY
<br />2009-10	Amended
<br />June15,2010	Through FY
<br />2009-10
<br />LandBuildin	$15,971,564	($450,000)	$15,521,564
<br />Design	$0	$0	$0
<br />Construction	$0	$0	$0
<br />Eno River Confluence Pro erty	$250,000	$0	$250,000
<br />Kirby Pro erty	$1,458,013	$0	$1,458,013
<br />Total Costs	$17,679,577	($450,000)	$17,229,577
<br />Section 5. The following amounts have been transferred to other County Capital
<br />Projects: