<br />5.1.5 Applications for Payment shall indicate the percentage of completion of each portion of the <br />Work as of the end of the period covered by the Application for Payment. <br />5.1.6 Subject to other provisions of the Contract Documents, the amount of each progress pay- <br />ment shall be computed as follows: <br />.~ Take that portion of the Contract Sum properly allocable to completed Work as deter- <br />mined by multiplying the percentage completion of each portion of the Work by the <br />share of the Contract Sum allocated to that portion of the Work in the schedule of val- <br />ues, less retainage of ten percent ( ~ ~%). Pending final determi- <br />nation of cost to the Owner of changes in the Work, amounts not in dispute shall be <br />included as provided in Subparagraph 7.3.8 of AIA Document A2o1-1997; <br />.z Add that portion of the Contract Sum property allocable to materials and equipment <br />delivered and suitably stored at the site for subsequent incorporation in the completed <br />-' construction (or, if approved in advance by the Owner, suitably scored off the site at a <br />location agreed upon in writing), less retainage of ten percent ( ~ ~/o); <br />.a Subtract the aggregate of previous payments made by the Owner; and <br />.4 Subtract amounts, if any, for which the Architect has withheld or nullified a Certificate <br />for Payment as provided in Paragraph 9.5 of AIA Document A2or-1997. <br />5.1.7 The progress payment amount determined in accordance with Subparagraph 5.r.6 shall be <br />further modified under the following circumstances: <br />.t Add, upon Substantial Completion of the Work, a sum sufficient to increase the total pay- <br />ments to the full amount of the Contract Sum, less such amounts as the Architect shall <br />determine for incomplete N~ork, retainage applicable to such work and unsettled claims; <br />and (Subparagraph y.8.~ of ALa Document Azot-i9y; requires re{ease of applicable retainage upon <br />Substantial Cornpl~ation of YV'ork ea~ith consent of si.~rety, if any.) <br />z Add, if final completion of the Work is thereafter materially delayed through no fault of <br />the Contractor, any additional amounts payable in accordance with Subparagraph y.io.3 <br />of AtA Document Aaot-1997. <br />5.1.8 Reduction or limitation e}f retainage, if any, shall be as follows: <br />(!f it is intended, pr-tor to Su(~stantial Completion qr the entire 61%ork, to reduce or lirr~ii tha retairuige resulting <br />from the percentages inserted in Clauses 5. t.6. i and 5. i.6.2 nbove, and this is not explained elsewhere in the <br />C.'ontract Documents, insert here provisions for such reduction or limitation.) <br />~~~~ <br />5.1.9 Except with the Owner's prior approval, the Contractor shall not make advance payments <br />to suppliers for- materials or equipment which have not been delivered and stored at the site. oo~Qo <br />G~ <br />5.2 FINAL PAYMENT ©lgg7 q~q® <br />5.2.1 Final payment, constituting the entire unpaid balance of the Contract Sum, shall be made pip DOCUMENT A101-1997 <br />by the OwrieC t0 the Contractor when: OWNER-CONTRACTOR <br />.t the Contractor has fully performed the Contract except for the Contractor's responsibil- AGREEMENT <br />ity to correct Work as provided in Subparagraph rz..2.2 of AIA Document A2oi-1997, and The American Institute <br />to satisfy other requirements, if any, which extend beyond final payment; and of Architects <br />.x a final Certificate for Payment has been issued by the Architect. 1735 New vork Avenue, N.w. <br />Washington, D.C. 20006-5292 <br />.. _..__. _ ... ___. _:_~. ,_...- .~~ ...iu ...f.i.s .4. ..i•L~w. ~w Ln~l nme~r~aiitif <br />