Orange County NC Website
shown at that time to be incomplete or defective. Within thirty {30} days of receipt of any <br />deficiency list, the Contractor shall complete and correct all items on that fist along with alt <br />other Work required to achieve Final Completion of the Work. At any time prior to <br />completion of the period of warranty, the CMAR may submit to the Contractor supplemental <br />deficiency lists, in which case the Contractor shaft complete or correct any and all new <br />items identified on the supplemental deficiency fists within the time period stipulated in <br />paragraph 18.3 of these General Conditions. <br />21.3 The making and acceptance of Final Payment shalt constitute a waiver of ail claims by the <br />CMAR except: <br />a} Claims arising from unsettled liens or claims against the Contractor. <br />b} Defective Work or materials appearing after Final Payment. <br />c} Failure of the Contractor to perform the Work in accordance w'sth the Contract <br />Documents. <br />d} As conditioned in the Performance Bond. <br />e} Claims made prior to Final Payment which remain unsettled. <br />f} Amounts due arising under Articles 18 and 28 of these General Conditions. <br />g} Claims for recovery of overpayment based upon incorrect measurement, estimate, <br />or certificate. <br />21.4 The making and acceptance of Final Payment shall constitute a waiver of all claims by the <br />Contractor except those claims previously made in writing pursuant to paragraph 15.2 of <br />these Genera{ Conditions and not finally resolved. <br />Z1.5 The CMAR shall not be required to make Final Payment unless and until {i} the Designer <br />has certified based on the Designer's observations and information that all of the Work by <br />the Contractor under the Contract Documents has been completed in accordance with the <br />Contract Documents, and (ii) the Work by the Contractor has been approved by al[ federal, <br />state and Local agencies having Jurisdiction. <br />21.6 ~ The final Request for Payment shall be identified on its face as such and shalt be <br />presented by the Contractor to the CMAR within thirty {30) days of completion of the Work. <br />Final payment of the retained amount due the Contractor. shad be made by the CMAR <br />within thirty (3©) days after the later of (i) full and Final Completion of all Work required of <br />the Contractor by the Contract Documents, and certification of such Work in accordance <br />with paragraph 21.5, {ii} submission of the affidavits and other documentation required by <br />Article 22; (fit} submission by the Contractor of a Request for Payment identified on its face <br />as final. <br />ARTICLE 22. CONTRACTOR, SUBCONTRACTOR AND SLIPPLtER AFFIDAVIT <br />22.1 The Final Payment due the Contractor on account of the Contract Documents shalt not <br />become due until the Contractor has furnished to the CMAR: (A) an affidavit by the <br />Contractor signed, sworn, and notarized to the effect that ati payments for materials, <br />services,- or for any other reason in connection with the Work or performance of the <br />Contract Documents have been satisfied and that no claims or liens exist against the <br />Contractor in connection with the same; (8} affidavits from each Subcontractor and supplier <br />signed, sworn, and notarized to the effect that {i} each such Subcontractor or supplier has <br />been paid in Tuft by the Contractor for all Work performed andlor materials supplied by it in <br />GENERAL CONDITIONS FOR CM AT RISK PROJ7=CT 37 of 42 JUNE 2007 ED1TlCiV <br />