Orange County NC Website
Plan approval by the County Commissioners on June 10, 2010 will allow the project to be <br />developed commensurate with the following timeline: <br />Demolition would be commenced under a contract issued by the Manager over the summer. <br />FINANCIAL IMPACT: Funding is available for project components as follows: <br />• Project # 30035 —Link Center Upfit; approximately $520,000 <br />o $425,000 of which will be funded via alternative financing approved by County <br />Commissioners in April 2009; to be sold in FY 2011. <br />• Project # 30018 —HVAC Projects; $90,777 <br />• Project #30019 —ADA Compliance; $65,595 <br />• Project # 30023 — Building Entry and Access Systems; $75,000 <br />Bids reflecting actual costs will be presented to County Commissioners for approval after the <br />summer break. <br />RECOMMENDATION: The Manager recommends the County Commissioners review and <br />approve the revised schematic design; and authorize staff and the Architect to proceed with <br />construction documents and bidding as outlined herein. <br />