OfZp- ~UC~- ~ Cog 23
<br />Pathways Elementary
<br />Orange County Schools
<br />Capital Project Ordinance
<br />Be it ordained by the Orange County Board of County Commissioners that pursuant to
<br />Section 13.2 of Chapter 159 of the. General Statues of North Carolina, the following capital
<br />project ordinance is hereby adopted.
<br />Section 1. The project authorized provides funds for the Construction of Pathways
<br />Elementary_ School.
<br />Section 2. The officers of the County are hereby directed to proceed with the budget
<br />contained herein.
<br />Section 3. The following revenue is anticipated to complete this project:
<br /> FY 2009-10
<br />Current FY 2009-10
<br />Amendment FY 2009-10
<br />Revised
<br />State Bonds $5,942,751 (5,942,751) $0
<br />1997 Bonds 5,800,000 (5,800,000) $0
<br />Im act Fees 1,053,543 (1,053,543) $0
<br />A ro riated Fund Balance 0 0 $0
<br />Transfer From Gen Fund 7,700 (7,700) $o
<br />From School Ca ital Res Fd 210,087 (210,087) $0
<br />Total Fundin $13,014,081 13,014,081) $0
<br />Section 4. The following amount is appropriated for this project:
<br /> FY 2009-10
<br />Current FY 2009-10
<br />Amendment FY 2009-10
<br />Revised
<br />Land $994,450 994,450 $0
<br />Professional Services 325,000 325,000 $0
<br />Water & Sewer 1,468,000 1,468,000 $0
<br />Construction 7,826 486 7,826,486 $0
<br />Access Lane 202,191 202,191 $0
<br />E ui ment 500 000 500,000 $0
<br />Startu Costs 235,000 235,000 $0
<br />Contin enc 1,341,726 1,341,726 $0
<br />Other 121,228 121,228 $0
<br />Total Fundin $13,014,081 13,014,081 $0
<br />Section 5 This ordinance supersedes previous Project Ordinances for this project.
<br />Section 6 The project now being complete, the Board of County Commissioners declares the
<br />project closed effective November 5, 2009.
<br />Adopted this 17th day of November 2009.