2
<br />2) Correction of Funding Source -The County Capital Project Fund project ordinances listed
<br />below correct the method used to move funds from one project to another. In past years funds
<br />have been moved from one project to another by intrafund transfers. This is not "best practice" in
<br />the accounting industry and should not be done for the following reasons:
<br />1) Transfers are only to be used for budgeted movements between funds, not for budgeted
<br />movements within the same fund. The use of transfers within the same fund will result in an
<br />inflated figure for both the budgeted amount of money and the actual amount of money in the
<br />fund.
<br />2) The use of transfers between projects can obscure the actual source of funds being used to
<br />pay for any one project, thus making it difficult to track and properly account for the use of
<br />restricted fund sources such as debt financing and grants.
<br />The best practice is to reduce the funding source of the project from which funds are being moved.
<br />Conversely the project receiving additional funding will show an increase in its fund source. In the
<br />chart below, projects with the same number followed by a letter indicate those projects in which funds
<br />were first reduced (project "A°) and then increased (project "B°), thus correcting the inappropriate
<br />"transfer" between projects.
<br />The current Project Ordinance budgets for Homestead Aquatics and Southern Park are also out of
<br />balance by offsetting amounts. Project ordinances 8A and 8D correct those balances.
<br />The Twin Creeks (Moniese Nomp) Park Project Ordinance 6C, Lands Legacy Project Ordinance 8B
<br />and Northem Human Service Center (now Cedar Grove) Park Ordinance 8C are being amended to
<br />align revenues with expenditures by including the remaining funding ftom the April 2009 Altemative
<br />Financing and future financing.
<br />In addition, Central Recreation Repairs Ordinance 5A is being reduced by $51,060 to provide funding
<br />needed to cover over expended budgets in the Greenways Development project and Homestead
<br />Community Center project.
<br />D1~~ /
<br />~~a4 D°i
<br /> Capital Project Ordinance Account
<br />(r) revenue (e) expense Amount
<br />debit Account
<br />(r) revenue (e) expense Amount
<br />credit
<br />5A Central Recreation Re irs (r) 2/3rds Bonds 5111,060 (e) Transfer to other proj 560,000
<br /> (e) Construction 551,060
<br />5B Homestead Communi Ctr (r) Transfer from other proj 560,000 (r) 2l3rds Bonds 577,634
<br /> " "~ _ (e) Sewer Connection $17,634
<br />6A Soccer Su erfund (r) 2001 Bonds 52,000,000 (e) Trensfer ~ other proj 52,000,000
<br />6B West Ten Soccer Com lex (r) Transfer from other proj 51,350,000 (r) 2001 Bonds 51,350,000
<br />6C Twin Creeks Park (r) Transfer from other proj 5650,000 (r) Altemative Financing 51,000,000
<br /> " (r) 2001 Bonds 5350,000
<br />' 7 Greenwa s Develo ment (r) 2001 Bonds 5575,000 (e) Transfer to other proj 51,000,000
<br /> " " (r) Transfer from other proj 5425,000 (r) Z/3rds Bonds 533,426
<br /> " " (e) Construction a33 426
<br />8A Homestead A uatics (e) Contribution to Ch Hill
<br />52,809,508
<br />(e) Transfer to other proj
<br />53,175,000
<br /> " (r) 2001 Bonds 5500,000 (r) Alternative Financing 5500,000
<br />8B Lands L aC (r Transfer from other proj 51,750,000 (r) 2001 Bonds 51,635,364
<br /> " " (e) Land 8 Associated Fees 52,825,300 (e) Hillhouse Rd Property 5300
<br /> " (e) Blackwood Property 51,268,116 (e) Other 51,408,897
<br /> " (e) Lewis Heardeaf Presve 61,145 (r) Alternative Financing 52,800,000
<br />8C Northem Human Svc Ctr Park r Transfer from other ro 5500,000 (r) Alternative Financing 5500,000
<br />8D Southern Park (r) Transfer from other proj 5925,000 ((r) 2001 Bonds 5925,000
<br /> " " {e) Contribution to Ch Hill 5365,492
<br />9 Bolin Creek Greenwa (r) Transfer from other proj 575,000 ((r) 2001 Bonds 575,000
<br /> Fund Total 516,591,681 516,591,681