• <br />ORANGE COUNTY <br />Board of Commissioners <br />Action Agenda Item Abstract <br />Meeting Date: March 9, 1999 <br />Subject: WTMP Expansion Proposal <br />Action Agenda <br />Item No. H. A. <br />Department: HEALTH Public Hearing Yes X No <br />Budget Amendment Needed Yes X No <br />Attachments(s): WTMP Expansion Proposal Information Contact: <br />System & Inspection Estimates Health Director's Office X2411 <br />Scenarios for Fees/General Fund Division Telephone Number <br />Letter from OWASA Hillsborough - 732 -8181 <br />Applicant Guide to Environmental Health Permits Chapel Hill - 968 -4501 <br />Mebane - 227 -2031 <br />Durham - 688 -7331 <br />Purpose: To review the proposal for the Wastewater Treatment Management Program (WTMP) Expansion and <br />consider inclusion of the proposal as a BOCC adopted goal. If approved to go forward, additional work needs to <br />be done regarding funding methods and detailed costs. <br />• Background: The current Wastewater Treatment Management Program (WTMP) was approved by the Board of <br />Commissioners in 1995. The program inspects non - municipal discharging wastewater systems and municipal <br />sludge sites. These are commonly called "alternative systems" and include low pressure pipe systems, pump <br />conventional systems, large systems, discharging sand filters, and non - municipal package plants, in addition to <br />sludge application sites. That program has been in operation and that Board goal is complete except for the <br />financial surety rules which are in the County Attorney's hands, and the delinquent fee actions which the attorney <br />has advised us not to pursue at this time. In June 1998, the Board of Health formed an ad -hoc committee to <br />prepare a proposal for an expansion of the WTMP to include gravity flow septic systems in the WTMP <br />framework. These are commonly called "conventional systems." The impetus for this expansion came from two <br />separate meetings in late springlearly summer of 1998. In a joint BOCC and OWASA meeting and in a <br />subsequent Board of Health meeting it was recognized that existing failure rates are not likely to improve without <br />action and that centralized wastewater disposal will not be a repair option in many areas of the county in the <br />foreseeable future. <br />The ad -hoc committee included representatives from OWASA, the BOCC, the Board of Health and the health <br />department staff. The Board directed the committee to look at three components for the expansion; education, <br />homeowner incentives and periodic re- inspections. The attached proposal was developed by the committee and <br />presented to the Board of Health for action at their November meeting. The Board of Health thoroughly discussed <br />the proposal and chose the Water Quality Critical Areas of the county as the preferred starting point of the <br />program and felt that a hybrid model of funding would be an appropriate option. The plan has a heavy emphasis <br />on homeowner education —both at the onset of the program and as part of the continuing effort. <br />Since the Board of Health meeting in November, additional staff work has been done that estimates the numbers <br />of systems within the Water Quality Critical Areas and in the watersheds as a whole in order to better predict the <br />phase -in need for staffing. <br />• <br />1 <br />