§ 3.4.18 Providing services after issuance to the Owner of the final Certificate for Payment, or in the absence of a final
<br />Certificate for Payment, more titan 60 days after the date of Substantial Completion of the Worlc.
<br />§ 3.4.19 Providing services of consultants for other than architectural, structural, mechanical and electrical engineering
<br />portions of the Project provided as a part of Basic Services.
<br />§ 3.4.20 Providing any other services not otherwise included in this Agreement or not custom -ily. furnished in
<br />accordance with generally accepted architectural practice.
<br />ARTICLE 4 OWNER'S RESPONSIBILITIES
<br />§ 4.1 The Owner shall provide full information in a timely manner regarding requirements for and limitations on the
<br />Project, including a written program which shall set forth the Owner's objectives, schedule, constraints and criteria,
<br />including spacerequirements and relationships, flexibility, expaldaUility, special equipment, systems and site
<br />requirements. The Owner shall furnish to the Architect, within. IS days after receipt of a written request, information
<br />necessary and relevant for the Architect to evaluate, give notice of or enforce lien rights.
<br />§ 4.2 The Owner shall establish and periodically update an overall budget for the Project, including the Construction
<br />Cost, the Owner's other costs. grid reasonable contingencies related to all of these costs.
<br />§ 4.3 The Owner;shall designate a representative authorized to act on the Owner's behalf with respect to the Project. The
<br />Owner or such designated representative shall render decisions in a timely manner pertaining to documents submitted
<br />by the Architect`in order to avoid unreasonable delay in the orderly and'sequential progress of the Architect's services.
<br />§ 4.4.The Owner shall furnish. surveys to describe physical c~iaracteristics, legal limitations and utility locations for the
<br />site .of the Project, and a written legal description of the srte' The surveys and legal information shall include;;as
<br />applicable, grades and lines of streets, alleys, pavements and adjoining property and structures; adjacent drarnage;
<br />~.:
<br />rights-of--way, restrictions, easements, encroachments, zoning, deed restrictions, boundaries and contours of the site;
<br />locations,' dimensions and necessary data' with respect to existing buildings, other improvements and ai'ccs; and
<br />information concerning available utility services and lines, both public and private, above and below grade, including
<br />inverts and depths. All the information on the survey shall be referenced to a Project benchmark.
<br />§ 4.5 The Owner shall furnish the services of geotechnical engineers when such services are requested by the Architect.
<br />Such services may include but are not limited to test borings, test pits, deteriunations of soil bearing values, percolation
<br />tests,>evaluations of hazardous materials, ground corrosion tests and resistivity tests, including necessary operations for
<br />anticipating strbsoil conditions, with reports and appropriate recommendations.
<br />§ 4.6 The Owner shall furnish the services of consultants other than those designated in Section 4.5 when such services
<br />are requested by the Architect and are reasonably required by the scope of the Project.
<br />§ 4.7 The Owner shall furnish structural, mechanical, and chemical tests; tests for air and water polltrtion; tests for
<br />hazardous materials; and other laboratory and environmental tests, inspections and reports required by law or the
<br />Contract Documents.
<br />§ 4.8 The Owner shall furnish all legal, accounting and insurance services that may be necessary at any time for the
<br />Project to meet the Owner's needs and interests. Such services shall include auditing services the Owner may require to
<br />verify the Contractor's Applications for Payment or to aseeiā¢Cain how or for what purposes the Contractor has used the
<br />money paid by or on behalf of the Owner.
<br />§ 4.9 The services, information, surveys.: and reports required by Sections 4.4 through 4.8 shall be,fnrnishedat the
<br />Owner's expense, and the Architect shall be entitled to rely upon the accuracy and completeness th,~reof.
<br />§ 4.10 The Owner shall provide prompt written notice to the Architect if the Owner becomes aware of any fault or defect
<br />in the Project, including any errors, omissions or inconsistencies in the Architect's Instzuments of Service.
<br />AIA Document 8151Tr^ -1997. Copyright ©1974, 1978, 1987, and 1997 by The American Institute of Architects. All rights reserved. WARNING: This
<br />AIA®Document is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of this AIA®Document, 7
<br />or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law.
<br />Purchasers are permitted to reproduce ten (10) copies of this document when completed. To report copyright violations of AIA Contract Documents, a-mall
<br />The American Institute of Architects' legal counsel, copyright@aia.org.