18.4 In the eleventh calendar month after Substantial Completion of the entire Project, and at <br />the request of the CM, the Contractor, the CM, the Owner and the Designer shall make an <br />inspection of the Work for the purpose of identifying defective workmanship and/or <br />materials. If the Contractor, having been requested to do so by the CM, fails to participate <br />in such inspection, the Contractor shall be conclusively bound by any decision or ruling by <br />the Designer as to any defective workmanship or material and. as to the Contractor's <br />responsibility for its repair or replacement. <br />ARTICLE 19. CM'S RIGHT TO DO WORK <br />19.1 If, during the progress of the Work or during any period of guarantee, the Contractor fails to <br />prosecute the Work properly or to perform any provision of the Contract Documents, the <br />CM, after three (3) days written notice to the Contractor from the CM, may perform or have <br />performed that portion of the Work and may deduct the cost thereof from any amount due <br />or to become due the Contractor. Notwithstanding any action by the CM under this <br />paragraph, all warranties and bonds given or to be given by the. Contractor shall remain in <br />effect or shall be given by the Contractor. <br />19.2 Should the cost of such action by the CM exceed the amount due or to become due the <br />Contractor, the Contractor and the Contractor's sureties shall be liable for and shall pay to <br />the CM the amount of such excess. <br />ARTICLE 20. PARTIAL PAYMENTS <br />20.1 Within thirty (30) days after initial receipt of the Construction Agreement by the Contractor <br />for signatures the Contractor shall submit to the CM a Schedule of Values. The Schedule of <br />Values shall indicate the value of the Work, including applicable overhead and profit, for <br />each Division and section of the Project Specifications. The CM shall be provided with the <br />Contractor's estimating work papers, Subcontractor agreements, supplier quotes, or other <br />documents substantiating these values if so requested in writing by the CM. The Contractor <br />shall provide the requested documentation within seven (7) days after receipt of the CM's <br />written request. The Schedule of Values shall be subject to approval by the CM and the <br />Owner, and if the CM and the Contractor cannot agree upon the Schedule of Va-ues, the <br />Designer shall prepare it, and the Schedule of Values as prepared by the Designer shall be <br />binding on the CM and the Contractor. No Request for Payment shall be certified by the <br />CM until the Schedule of Values has been approved by the Owner. <br />20.2 Not later than the fifth (5th) day of each calendar month the Contractor shall submit to the <br />CM a Request for Payment for Work done during the previous calendar month. The <br />Request for Payment shall be in form of AIA Document G702 (latest edition), or other <br />published document approved by the CM, and shall show substantially the value of Work <br />done (including the value of material delivered to the Project or stored by the Contractor at <br />another site, subject to the conditions hereinafter set forth) during the previous calendar <br />month, and shall sum up the financial status of the Work with the following information: <br />a) Total Contract Price, including any adjustment thereto. made pursuant to the <br />Contract Documents. <br />b) Value of Work completed and materials properly stored to date. <br />c) Less amount retained. <br />d) Less previous payments. <br />e) Current amount due. <br />GENERAL CONDITIONS FOR CM AT RISK PROJECT 35 of 43 JUNE 2007 EDITION <br />